BUSI 313 Quiz 3

BUSI 313 Quiz 3 Liberty University

Set 1

  1. The risk identification process should be limited to just the core project team.
  2. The project being delayed is an example of a major risk that should be assessed.
  3. A risk profile is a list of questions that have been developed and refined from previous, similar projects.
  4. Which of the following is NOT one of the potential responses to a specific risk event?
  5. A fixed price contract is an example of
  6. If, during risk response development, you successfully identify how you will respond to a risk, contingency planning is unnecessary.
  7. Having an environment where identified risks are treated professionally will lead to better control of risks.
  8. A risk is an uncertain event that, if it occurs, can have a positive or negative effect on project objectives.
  9. When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.
  10. In a resource-constrained project the third priority in assigning resources is usually given to activities with the
  11. If resources are not adequate to meet peak demands, the resulting reschedule is termed
  12. Since resource leveling or smoothing delays noncritical activities, a common result is a decrease in network sensitivity.
  13. Which of the following is NOT one of the more common problems associated with scheduling multiproject resources?
  14. Comparing Planned Costs versus Actual Costs will give the project manager a quick understanding of the status of the project.
  15. These are all guidelines a project manager should consider when EXCEPT
  16. Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will he decide which activity should be scheduled first?
  17. Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
  18. When determining which activity to crash, there are other factors that should be assessed beyond cost. Which of the following is NOT one of these factors?
  19. Resources are frequently over-allocated when crashing a schedule.
  20. Which of the following correctly calculates an activity’s cost slope?
  21. Which of the following projects would be least benefited if additional resources were added?
  22. One way of reducing project costs is identifying tasks that _________ can do themselves.
  23. When crashing a schedule, this may set in when a least-cost method is used.
  24. Crashing frequently results in over allocation of resources.
  25. Brooks’ law states that adding manpower to a software project helps keep it on schedule.

Set 2

  1. A risk profile is a list of questions that have been developed and refined from previous, similar projects.
  2. is a measure of how easy it would be to notice that a risk event was going to occur in time to take mitigating action, that is, how much warning you would have.
  3. A key distinction between a risk response and a contingency plan is
  4. A list of questions that address traditional areas of uncertainty on a project is termed a
  5. The chances of a risk event occurring as a project proceeds through its life cycle tend to
  6. The initial step in the risk management process is to
  7. Organizations use __________ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk.
  8. Risks are evaluated in terms of
  9. The level of resources each activity will need to be completed in the given amount of time has been estimated; therefore, there are no resource constraints.
  10. A special truck that George needs on his project has been scheduled on another project. This is an example of what type of resource constraint?
  11. Why is it necessary to have a time-phased budget baseline?
  12. Resource constraints can be overcome by creative and efficient scheduling.
  13. All of the following are types of resource constraints EXCEPT
  14. When leveling schedules to overcome resource constraints, ___________ is increased.
  15. If resources are truly limited and activity time estimates are accurate, the resource-constrained schedule will materialize as the project is implemented, not the time-constrained schedule.
  16. When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.
  17. The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.
  18. Crashing can negatively impact the morale and motivation of the project team.
  19. Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an example of reducing project duration caused by
  20. The relationship between the normal point and the crash point is assumed to be
  21. Because direct costs are assumed to be developed from “normal” methods and in a “normal” amount of time, any reduction in activity time should add to the costs of the activity.
  22. Crashing activities on a project network that is sensitive could increase the risk of the project being late.
  23. Which of the following is NOT considered a project indirect cost?
  24. Crashing frequently results in over allocation of resources.
  25. When a project manager must reduce project duration but resources are constrained, creating a software program that will have fewer features than originally planned or building a house without the bonus room the owner originally specified in the plans would both be examples of
Continue reading CRIS 605 Quiz Final

CRIS 605 Quiz Final

Price: $4.00

CRIS 605 Quiz Final Once a woman decides to leave the battering relationship, comes to an abuse shelter, and regains some psychological equilibrium, the crisis worker’s first job is to provide immediate practical advice on such issues as finding a place to live, child care, financial aid, etc. When women finally decide to end the…

Purchase
Continue reading WRSP 101 Quiz 4

WRSP 101 Quiz 4

Price: $4.00

WRSP 101 Quiz 4 WRSP 101 Quiz Discipleship Principles for Worship All of the following are benets of sustaining a choir ministry as part a church’s worship team, EXCEPT: Every Christian has a vocational calling to serve as a leader of worship. As worship leaders who strive to connect people to God through music we…

Purchase
Continue reading WRSP 101 Quiz 3

WRSP 101 Quiz 3

Price: $4.00

WRSP 101 Quiz 3 WRSP 101 Quiz History of Worship The Pre-Reformation clergyman best known for his belief that the Bible should be available to all people and in a language they could understand, not just Latin, was: “The Lord Is My Banner” is: The Roman Catholic clergy (prior to the Reformation) saw all congregants…

Purchase
Continue reading WRSP 101 Quiz 2

WRSP 101 Quiz 2

Price: $4.00

WRSP 101 Quiz 2 WRSP 101 Quiz Old and New Testament Worship The five books of psalms were written to correspond with: Which is not one of the lessons learned from Jehoshaphat’s war strategy? __________ led in the worship of the Israelites after God delivered them from captivity in Egypt. Out of the 38,000 members…

Purchase
Continue reading WRSP 101 Quiz 1

WRSP 101 Quiz 1

Price: $4.00

WRSP 101 Quiz 1 WRSP 101 Quiz Foundational Studies of Worship To experience honest worship that is dynamic and delightful, I must . . . The text notes a key passage of Scripture instructing us to worship God in the beauty of ______________. The short definition of the word, “worship” is . . . God…

Purchase
Continue reading EDUC 787 Powerpoint Assignment

EDUC 787 Powerpoint Assignment

Price: $3.99

EDUC 787 Reflective PowerPoint Presentation Assignment The candidate will create a PowerPoint presentation exploring one of the course topics more in depth. Additionally, the candidate must type a script to align with the PowerPoint for a 30-minute presentation incorporating relevant sources. $3.99 – Purchase Checkout Added to cart You May Also Like EDUC 787 Media Analysis Assignment…

Purchase