BUSI 313 Quiz 2

BUSI 313 Quiz 2 Liberty University

Set 1

  1. If the project time should be accepted, then the project must be completed on time.
  2. The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called
  3. One way for a project manager to communicate the authority granted to individual project members is to publish a
  4. A communication plan is a key component for giving guidelines on how to track project
  5. Which of the following is NOT true regarding scope creep?
  6. The highest element in the hierarchical breakdown of the WBS is the first major deliverable for the project and the lowest element is a work package.
  7. “Reviews with customer” only refers to projects with external customers who are paying for the project.
  8. There is a strong correlation between project success and clear project scope definition.
  9. Which of the following is least likely to be included in a work package?
  10. Which of the following does NOT help describe a bottom-up estimating approach?
  11. The salary of the project manager would be an example of what type of cost found in a project?
  12. Which of the following is a good condition for top-down estimating?
  13. Organization culture can significantly influence project time and cost estimates.
  14. Which of the following would best represent direct project costs?
  15. Refining estimates may be necessary for a number of reasons. For example, design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are good examples of
  16. The salary of the project manager and her administrative assistant is classified as direct labor costs.
  17. An external view of a Mega Project based upon the outcome of similar projects undertaken in the past is known as:
  18. Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of
  19. A sequence of connected, dependent activities is termed a(n)
  20. When translated into a project network, a work package will become
  21. Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them).
  22. Which of the following represents an activity on an activity-on-node (AON) project network?
  23. Activities which can take place at the same time are termed
  24. An activity is an element of the project that always requires time.
  25. The likelihood the original critical path(s) will change once the project is initiated is referred to as

Set 2

  1. Creating a communication plan typically follows a process that begins with a stakeholder analysis.
  2. If the project time should be accepted, then the project must be completed on time.
  3. All of the following are usually included in a work package EXCEPT
  4. The final stage in defining a project is coding the organization breakdown structure or OBS for the information system.
  5. The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called
  6. The _________ is used to assist in making project trade- offs among schedule, budget, and performance objectives.
  7. In reviewing the project plan, Susan sees that the first prototype must be completed by October 12. This would be best classified as a
  8. For large companies, the organization breakdown structure is used rather than the work breakdown structure.
  9. If a project criterion should be optimized if at all possible, it is classified as being constrained.
  10. Which of the following is NOT true in regard to the level of detail estimates should contain?
  11. The consensus method of estimating costs is a bottom- up technique.
  12. The ideal approach to estimating project time and costs is to use both the top-down and the bottom-up approach.
  13. Benefits of Reference Class Forecasting include
  14. While it may be true that Mega Projects are by nature extremely difficult to estimate, another factor identified in the consistent pattern of estimating difficulties is:
  15. Large projects that have long time horizons and a very high complexity can be referred to as
  16. An external view of a Mega Project based upon the outcome of similar projects undertaken in the past is known as:
  17. The salary of the project manager would be an example of what type of cost found in a project?
  18. Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of
  19. The forward pass in project network calculations determines all of the following EXCEPT
  20. Which of the following can be used without coordinating with managers of succeeding activities?
  21. Arrows on an activity-on-node (AON) project network represent
  22. When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case you select the smallest early finish number of all its immediate predecessor activities.
  23. Information to develop a project network is collected from the
  24. A(n) _________ activity has more than one dependency arrow flowing from it.
  25. When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
Continue reading CRIS 605 Quiz Final

CRIS 605 Quiz Final

Price: $4.00

CRIS 605 Quiz Final Once a woman decides to leave the battering relationship, comes to an abuse shelter, and regains some psychological equilibrium, the crisis worker’s first job is to provide immediate practical advice on such issues as finding a place to live, child care, financial aid, etc. When women finally decide to end the…

Purchase
Continue reading WRSP 101 Quiz 4

WRSP 101 Quiz 4

Price: $4.00

WRSP 101 Quiz 4 WRSP 101 Quiz Discipleship Principles for Worship All of the following are benets of sustaining a choir ministry as part a church’s worship team, EXCEPT: Every Christian has a vocational calling to serve as a leader of worship. As worship leaders who strive to connect people to God through music we…

Purchase
Continue reading WRSP 101 Quiz 3

WRSP 101 Quiz 3

Price: $4.00

WRSP 101 Quiz 3 WRSP 101 Quiz History of Worship The Pre-Reformation clergyman best known for his belief that the Bible should be available to all people and in a language they could understand, not just Latin, was: “The Lord Is My Banner” is: The Roman Catholic clergy (prior to the Reformation) saw all congregants…

Purchase
Continue reading WRSP 101 Quiz 2

WRSP 101 Quiz 2

Price: $4.00

WRSP 101 Quiz 2 WRSP 101 Quiz Old and New Testament Worship The five books of psalms were written to correspond with: Which is not one of the lessons learned from Jehoshaphat’s war strategy? __________ led in the worship of the Israelites after God delivered them from captivity in Egypt. Out of the 38,000 members…

Purchase
Continue reading WRSP 101 Quiz 1

WRSP 101 Quiz 1

Price: $4.00

WRSP 101 Quiz 1 WRSP 101 Quiz Foundational Studies of Worship To experience honest worship that is dynamic and delightful, I must . . . The text notes a key passage of Scripture instructing us to worship God in the beauty of ______________. The short definition of the word, “worship” is . . . God…

Purchase
Continue reading EDUC 787 Powerpoint Assignment

EDUC 787 Powerpoint Assignment

Price: $3.99

EDUC 787 Reflective PowerPoint Presentation Assignment The candidate will create a PowerPoint presentation exploring one of the course topics more in depth. Additionally, the candidate must type a script to align with the PowerPoint for a 30-minute presentation incorporating relevant sources. $3.99 – Purchase Checkout Added to cart You May Also Like EDUC 787 Media Analysis Assignment…

Purchase